Chongqing Fuels Clustering of Municipal-Level Key Projects

The National Hydrogen Energy Quality Supervision and Inspection Center, a municipal-level key project located in Yufu New Town, Liangjiang  New Area, is speeding up the construction progress.

The construction of the laboratory and the testing of the experimental equipment in the temporary workshop are carried out simultaneously.

The Center has entered the stage of foundation construction, where the site leveling has been generally completed, and the construction of the laboratories of vehicle and fuel cell is about to commence, according to the relevant person in charge of Liangjiang New Area.

The project is expected to be concluded by the end of 2021 when the performance tests of fuel cells and vehicles of hydrogen-fueled vehicles can be carried out to advance the upgrade of China's automobile industry.

Meanwhile, as the construction of the laboratories, the Center has completed the bidding for all the major equipment. In addition, the tests of the fuel cell system had also been finished during the Labor Day holiday, indicating that the Center has the core capability of testing hydrogen-fueled vehicles.

In addition, at the construction site of the Dadi (International) Life Science Park, several buildings have sprung up after the roofing.

An effect picture of Dadi (International) Life Science Park after its construction gets done. (Photo/ Liangjiang New Area)

Dadi (International) Life Science Park, located in the Shuitu New Town of Liangjiang New Area, is an expansion of Dadi Enterprise Park and a professional biomedical, industrial park supported by the city.

The park is estimated to embrace more than 150 Chinese and foreign biomedical enterprises upon its completion, with a total output value of about 30 billion yuan (about 4.63 billion U.S. dollars).

At present, 50% of the first batch of industrial housing covering 120,000 square meters in phase I of the project has been capped, while the construction of an exterior wall and landscape engineering will be accelerated and completed in July this year.

Phase I of the project is scheduled to be completed and delivered to the settled enterprises after the 2022 Spring Festival.